Distribution Warehouse, Dandenong
Industrial · Case Study

Distribution Warehouse, Dandenong

System
Heavy-Duty Epoxy + Line Marking
Size
1,400 m²
Duration
1 week
Category
Industrial
Brief

The problem

Existing slab was tired, with surface cracking and an inconsistent finish. The owners wanted a single, premium surface — durable enough for daily use and beautiful enough to be on display.

Approach

The solution

Diamond grinding to CSP 2, joint stitching, two coats of Heavy-Duty Epoxy + Line Marking laid over two working days with a polyaspartic top coat.

Outcome

The result

A flawless, jointless, mirror-grade finish handed over inside the original quoted window. Walk-on same evening, drive-on the next day.